New Roundabout – A82 Fort William

27th February 2017

 

New Roundabout – A82 Fort William

upcoming works to be carried out on the A82 on North Road, Fort William. These works are programmed to commence on 13th March 2017.

As part of the contracted works for Morbaine Ltd who are building a retail development, the  works involve the following main activities;

  • Construction of new roundabout at the position of the existing Lochaber Smelter junction
  • Associated drainage works
  • Service diversions required for the works
  • Cycle path construction
  • Toucan crossing construction
  • Bus Stop layby construction
  • New street lighting installation works

 

I have attached a location plan and traffic management phasing drawings with associated durations for your information.

Gordon Nairn

Site Agent

 I & H Brown Site Office, North Road,Fort William,PH33 6TH

012 – A82 Location Plan012 – A82 Location Plan

C17161-IHB-00-XX-DR-C-1005_S3_P4

C17161-IHB-00-XX-DR-C-1004_S3_P4

C17161-IHB-00-XX-DR-C-1003_S3_P5

C17161-IHB-00-XX-DR-C-1002_S3_P4

 